Hawkinge Primary School
Project
Alterations to staff room including new windows, removal of walls, erection of stud partitions, new DDA toilet and new staff kitchen.
Key challenges:
- Timeframe; the project had to be completed within a 5-week period during the summer holidays 2021
- Discovery of existing structure was not as per the original plans, requiring a structural engineer to redesign the steelworks that supported the roof joists and ceiling
- Sourcing the additional workforce, materials and resources to meet the specification by the agreed deadline
Highlights:
- Collaboration with other professionals including the Local Authority to resolve issues in safe and timely manner.
- The final result exceeded the client’s original vision.
Contract Value
£50,000 – £55,000
Date
July 2021
Contract Period
6 weeks
Client
Hawkinge Primary School